Safety operating procedures and precautions for pile drivers


Release time:

Feb 02,2024

Hebei Xinhe Jizhong pile driver is located on the north side of National Highway 308 in Baishen Industrial Development Zone, Xinhe County, Xingtai City. It is adjacent to the Qingyin Expressway and has convenient transportation. It is a professional manufacturer specializing in the development, production, and sales of various pile drivers and steel reinforcement series products.

Strictly abide by the relevant maintenance regulations of the pile driver, conscientiously carry out maintenance at all levels, and ensure that the pile driver is always in good condition.

We specialize in producing various types of pile driving machines, including CFG pile driving machines, hydraulic walking type long spiral drilling machines, and submersible engineering drilling machines. Our main products include CFG series long spiral drilling machines with effective depths of 18, 20, 23, 26, 28, 30, and other models, which are operated by electric motors and hydraulic machines, and operate in a walking style. When working, a long spiral drilling rig is used to drill to the design elevation. When lifting the drill, concrete is poured into the pile through a concrete conveying pump (or steel cage can be inserted later), and the drilling and pile formation are completed synchronously by one machine. Our products have over 10 series and 30 varieties, selling well in 30 provinces, cities, and regions in China and exporting to 7 countries.
1、 The operator of the pile driver must be familiar with the structure, performance, operation essentials, and safety precautions of this machinery. Only after passing the exam and obtaining a certificate of conformity can they operate it independently.
2、 Operators must be trained and qualified before they can operate the machine. All staff should wear insulated shoes and safety helmets.
3、 Strictly abide by the relevant maintenance regulations of the pile driver, conscientiously carry out maintenance at all levels, and ensure that the pile driver is always in good condition. And pay attention to reasonable use and correct operation.
4、 Before starting the pile driver, the following preparations should be made: [What precautions should be taken when operating the pile driver]
1. Understand the construction conditions and tasks from the construction personnel, as well as the problems discovered during construction and the precautions that should be taken during this shift.
2. Adjust the position of the variable speed gear of the pile driver according to the vibration force required by the construction personnel.
3. Check if the insulation of cables and wires is good. Check if the controller contacts are in good condition and if the boundaries are correct.
4. Check if the voltage of the power supply meets the requirements.
5. Lubrication and maintenance of each department according to daily maintenance items.
5、 Safety precautions for pile drivers during operation:
1. When the pile driver is working, there should be a dedicated person to command it. Commanders and operators should check signals with each other before starting work. Close cooperation is necessary in work.
2. At the beginning, use an electric bell or other means to send a signal to notify surrounding personnel to leave.
3. The pile driver and pile cap, as well as the plane between the pile cap and the pipe column (or pile), should be leveled, and the connecting bolts should be tightened and checked regularly for looseness.
4. The starting of the pile driver should be accelerated from low speed to high speed step by step.
5. The pile driver should closely monitor the current and voltage indications on the control panel during operation. If abnormal noises or other abnormal situations are found, the machine should be stopped immediately for inspection.
6. Regularly check the bearing temperature and whether the bearing cover screws are loose. Strictly check whether the eccentric iron block connecting screws are loose to prevent accidents.
7. When sinking, it is strictly prohibited to stand around the pipe column (or pile).
8. When the pile driver cooperates with water injection and mud suction for sinking, relevant personnel should be contacted in advance and work should be carried out accordingly

Learn More About Industry Dynamics

Feb 02,2024

Safety operating procedures and precautions for pile drivers

Hebei Xinhe Jizhong pile driver is located on the north side of National Highway 308 in Baishen Industrial Development Zone, Xinhe County, Xingtai City. It is adjacent to the Qingyin Expressway and has convenient transportation. It is a professional manufacturer specializing in the development, production, and sales of various pile drivers and steel reinforcement series products.

Feb 02,2024

What are the main causes of pile foundation quality accidents

The quality of bored pile construction includes excessive sediment thickness, concrete segregation, mud inclusion in the pile body, failure to meet design requirements for concrete strength, and severe displacement and deformation of steel bars.

Feb 02,2024

Types and working principles of pile drivers

The drop hammer pile driver is a type of pile sinking equipment with the characteristics of simple design, easy installation and transportation, large impact force, and stable performance. It is a steel heavy block that is lifted by a hoist with a hook, and after being unhooked, it freely falls along the guide frame to drive the pile.

Feb 02,2024

Repair and maintenance of long spiral pile driver

The long spiral pile driver should regularly inspect the winch, column guide rail, rotating mechanism, rotating support, diagonal support adjustment mechanism, diagonal support screws, sprockets, guide wheels, and drive wheel brackets, and regularly add lubricating grease.